Section 3 of the Party Wall etc. Act 1996

Section 3 of the Party Wall etc. Act

Section 3 of the Party Wall etc. Act 1996 deals with the requirements for issuing a Party Structure Notice.

Before a building owner can exercise any right conferred to him under Section 2 of the Party Wall Act he should serve on an adjoining owner a Party Structure Notice stating his intentions.

What should a Party Structure Notice contain?

A party structure notice should be served to the adjoining owner 2 calendar months before the works are due to begin. Although there is no express requirement within this section to include a date on the notice it is implied by the Act’s stipulation of the notice period. The notice will cease to be effective if the works in which it relates do not begin within 12 months, beginning with the day of which the notice was served and if the work is not undertaken with due diligence.

A Party Structure Notice should include the name and address of the building owner, as well as the particulars and description of the proposed works. In cases where the building owner is seeking to construct special foundations, then plans, sections and details of these foundations, together with structural engineer calculations of the loads to be carried, should also be included. The notice should also include the date on which proposed works are due to commence.

Serving Notice

Notices under Section 3 of the Party Wall etc. Act pertain only to Section 2 of the Act. It is deemed by party wall professionals that the format of notices under this section should also be applied for notices of adjacent excavation as well as line of junction notices.

If a notice is not served then the Act is not invoked, nor are the rights conferred under the Act. Notice can be issued by anyone, although in our experience it can be easy for the lay person to make a mistake on a notice which can invalidate it. We advise clients that the cost is minimal and it is usually best to allow us to issue valid notice/s on their behalf. If an invalid notice is served there is a possibility that notice will need to reissued leading to inevitable delays. It should be noted that Party Wall Notices are legal documents.

When a notice is served by another party on behalf of the building owner it should be made clear that this is the case on the notice. The person serving notice should have written authority to do so. A party wall surveyor serving notice is acting as an agent at this stage, not a party wall surveyor. Party Wall Surveyors can only be appointed as a Party Wall Surveyor once a notice has been served and a dispute has arisen. Appointment of Surveyors is covered under Section 10 of the Act.

Agreement to a notice can be given at any time, even if the process of dispute has commenced. An adjoining owners consent to any notice must be in writing. Party wall notices become legally binding documents and any consent given needs to be documentable. This prevents any potential misunderstandings once works are underway.

If you require advice regarding Section 3 of the Party Wall etc. Act or indeed any Party Wall matter, contact us on 01635 579208.