Recently we have had a number of requests for information regarding party wall procedure. With the aim of providing guidance the following is an overview of the basic procedure of serving Party Wall notices:
1. Firstly, do you need to issue a party wall notice? For the sake of argument let’s say you do. Do you know what type of notice needs to be served? A line of junction notice? A party structure notice? Or a notice of adjacent excavation? In some cases it may be just one in some cases it may be all three. This can easily be determined by any good Party Wall Surveyor who knows the Party Wall Act.
2. Secondly, on whom are you serving notice? Who is the freeholder? Are there any leaseholders? Does the proposed work affect more than one structure? If so, there are likely to be a number of parties to whom notice must be served.
3. With the aforementioned identified notice can be served. RMA Surveyors Ltd are often asked to become involved in Party Wall matters after notice has been served. Clients sometimes see an early saving being made by not appointing a Party Wall Surveyor, as the process seems simple at the outset. However, as the process develops it can become more complex and Building Owners seek to appoint Party Wall Surveyors to untangle the knots. We would say two things at this juncture. Firstly, fees for initial notice are usually minimal. Secondly, issue of the correct, properly drafted notices at the outset will save time. If a notice is not correct, it is invalid and another valid notice must be served. It can take two months before works can start from date of issue of a valid notice.
4. Valid notice is served to the Adjoining Owner. They now have fourteen days to respond. The adjoining owner can assent or dissent to the proposed works. If the adjoining owner does not respond in this period, works are deemed to be in dispute. If the Adjoining Owner agrees to works, the Building Owner may, by written agreement, proceed with works. We strongly recommend a condition survey of the Adjoining Owner’s property be undertaken prior to works commencing, to provide a benchmark and avoid later dispute.
5. If no response is received or the Adjoining Owner dissents to works the building owner will need to write to the adjoining owner to request they appoint a Party Wall Surveyor. The Adjoining Owner may opt to use the Surveyor appointed by the Building Owner. They may prefer to appoint their own Surveyor. In most cases the fee for the Adjoining Owner’s Surveyor will be borne by the Building Owner.
6. Once appointed the Agreed Surveyor or Surveyors should then work to draw up a Party Wall Award. A Party Wall Award is the framework whereby works affecting the party structure are to be executed. A condition survey of the Adjoining Owner’s property will be undertaken. Once the Party Wall Award is agreed and published works can commence from the date stated within the Award.
Please also see our Party Wall Pitfalls blog with more useful guidance about the Party Wall process.